Roatan 2024 - 3/24

Project updates…
  • Kitchen floor is done, walls are framed and rough-in electrical is done
  • Apartment drywall 90% installed and 50% mudded
  • Ceiling boards are stained and 60% installed
  • 90 yards of fill dirt were added to the yard and under the facility, crew has been hired for another week to add another 90 yards under the lower section
  • Church was good, Bonnie shared her testimony and Dino taught from Proverbs 31 about a virtuous woman
  • The team enjoyed a play day at the beach